Raw Water Line Emergency Replacement

Rapid design for repairs

Our client detected a significant leak in a critical water supply line (feed water to the water treatment plant) with most of the watermain being located under existing buildings. LHB designed a new 30-inch diameter watermain so that maximum construction could be completed with the old watermain in place and minimal watermain tie-ins needing to be completed during a scheduled outage. Design work included extensive routing around existing pipes and structures and inserting pipe supports in tight quarters.

Project Type Mechanical piping
Location International Falls, MN
Completion Date April 2019
Market Pulp & Paper